MGD Project updates (LinkedIn post) – în limba engleză
București România, 4 June 2021
Late spring updates from our Gas Treatment Plant near Vadu: most of the foundations and steel structures are close to completion, the cold vent is fully installed, the mechanical, electrical and piping works are progressing constantly.
Sometime this summer we estimate to reach the peak of the works at the GTP.
We thank our BSOG team based there who maintained progress despite all challenges and to all workers on site who faced a spring rainier than usual.